Street Repairs Oct 6-13 (Avondale, Coronada, Hanover Court&Road, Las Vegas, Sue, Waverly, Westfield)

This was superseded by a notice issued by the City on Oct 9, 2020

https://www.a2elnel.com/post/updated-street-repairs-oct-6-16-avondale-coronada-hanover-las-vegas-sue-waverly-westfield



Attached is a copy of a construction notice that will be circulated to Avondale Avenue, Coronada Street, Hanover Court, Hanover Road, Las Vegas Drive, Sue Parkway, Waverly Road and Westfield Avenue property owners/residents regarding the final stages of resurfacing work on these local streets that will begin next week and continue into the following one.

Weather permitting; beginning Tuesday, October 6, 2020 through Tuesday, October 13, 2020 between 7:00 a.m. and 8:00 p.m. the City’s contractor, Cadillac Asphalt, will be performing cold milling/pavement removal, pavement/base repairs and grading, utility structure adjustments, and paving operations as shown below on Avondale Avenue, Coronada Street, Hanover Court, Hanover Road, Las Vegas Drive, Sue Parkway, Waverly Road and Westfield Avenue as a continuation of the work on the local street portion of the citywide 2020 Street Resurfacing Project.

  • Tuesday, Oct 6th Cold Milling: Coronada Street, Hanover Court, Las Vegas Drive and Sue Parkway

  • Wednesday, Oct 7th Cold Milling: Avondale Avenue, Hanover Road, Waverly Road and Westfield Avenue

  • Thursday, Oct 8th - Friday, Oct. 9th Pavement Repairs, Base Repairs and Grading: Intermittent work on potentially all streets

  • Saturday, Oct 10th Paving: Coronada Street, Hanover Court, Las Vegas Drive and Sue Parkway

  • Monday, Oct 12th Paving: Hanover Road, Westfield Ave and Waverly Road

  • Monday, Oct. 12th Utility Structure Adjustments: Hanover Court and Las Vegas Drive

  • Tuesday, Oct. 13th Paving: Avondale Avenue, Hanover Court and Las Vegas Drive


The contractor’s goal is to perform its construction operations with the least amount of inconvenience to residents. On these days, vehicular access to and from residences will be limited as intermittent closures and related delays will be present to accomplish these activities. Based on experience, the success of this work depends upon your assistance. Please kindly observe the following:

  1. Turn off all lawn sprinklers and keep the street free of all trash and recycle receptacles and/or bags, and compost carts.

  2. If you require use of your vehicle(s) during the times of planned work, it is highly recommended you park legally on an adjacent street during working hours.

  3. If you have a special circumstance that may interfere with this work, please advise the contractor’s site supervisor, Jay Wartella (269-209-4588), either of the City’s project inspectors, Gary Shivley (734-765-8154) or Carl Emmons (517-605-9342), or the City’s project manager, David Dykman (734-794-6410 ext. 43685). We will do our best to accommodate you.

  4. Weather and related scheduling conflicts may delay this work. Please visit the following website to obtain schedule updates: https://www.a2gov.org/departments/engineering/Pages/Construction-Projects.aspx

Thank you in advance for your patience and cooperation during this improvement project.