Hoover/Greene/Hill Project Update Nov 4th

The following update was emailed on Nov 4th, 2019 by Chris Wall, Project Manager for the City of Ann Arbor. For any questions or concerns with this project (or to be added to his email list of construction updates), he can be contacted at 734-794-6410 ext 43661 or by email at cwall@a2gov.org


The following work by the contractor is on-going this week:

  • Road work on Hill Street between Brown Street and Fifth Avenue.

  • Road work on Greene Street between Hoover Avenue and Hill Street.

  • If weather permits, we are planning to finish paving Hill Street and Greene Street later this week.

All major water main and storm sewer work has been completed. There are a couple water services being worked on and each property impacted by this work are being consulted with directly.


The Hill Street (between Brown and Fifth), Greene Street (between Hill and Hoover), and Fifth Avenue (at Hill) closures remain in effect. The suggested detour route is Madison to Main, to Hoover, to Division. 


Additional information about the Hoover, Greene, & Hill Improvement project is also available at a2gov.org/HooverGreeneHill

I previously posted about this project here:

https://www.a2elnel.com/post/hoover-greene-hill-project-update-oct-16th

https://www.a2elnel.com/post/hoover-greene-hill-project-update-sept-30th

https://www.a2elnel.com/post/hoover-greene-hill-project-update-sept-2nd

https://www.a2elnel.com/post/hoover-greene-hill-project-update-aug-26th

https://www.a2elnel.com/post/hoover-greene-hill-project-update-aug-12th

https://www.a2elnel.com/post/hoover-greene-hill-project-update-aug-5th

https://www.a2elnel.com/post/hoover-greene-hill-project-update-july-8th-includes-water-main-shutdowns-july-11-12

https://www.a2elnel.com/post/hoover-ave-traffic-control-plan-june-12th-to-july-26th

https://www.a2elnel.com/post/hoover-greene-hill-project-update-june-10th-includes-water-main-shutdowns

https://www.a2elnel.com/blog/hoover-greene-hill-project-update-june-3rd

https://www.a2elnel.com/blog/hoover-greene-hill-project-update-may-28th

https://www.a2elnel.com/blog/traffic-control-plan-may-6th-30th-on-hoover-ave

https://www.a2elnel.com/blog/hoover-greene-hill-construction-begins-may-6th

Recent Posts

See All

South Maple traffic control plan on Feb 11th

The following was issued by the City on Feb 10, 2020: Notice of Temporary Traffic Control Plan: South Maple Road between Pennsylvania Avenue and Pauline Boulevard ; Tuesday, Feb. 11, 2020 (7:00 AM - 3

South State Street detour Jan 8th

Notice of Temporary Traffic Control Plan South State Street, Between Hill Street and Packard Street Wednesday, Jan. 8, 2020 Location and Limits of Affected Area: South State Street, between Hill Stree

Elizabeth NELSON

DEMOCRAT for Ann Arbor City Council Ward 4

  • Email
  • Twitter
  • Instagram
  • Facebook
  • YouTube

Paid for by the Committee to Elect Elizabeth Nelson 

PO Box 2243. Ann Arbor. MI 48106-2243